Road construction progressing well despite payment delays: RA

21 Nov 2016 13:10pm
WINDHOEK, 21 NOV (NAMPA) – The Roads Authority (RA) said delayed capital road projects envisaged for the 2016/17 financial year will be completed by early next year.
RA Manager of Corporate Communications, Hileni Fillemon said in a media statement issued Friday, the Oranjemund-Rosh Pinah and Oshakati-Omungwelume-Ongenga road construction projects are expected to be completed by May and March 2017, respectively.
All works on Section Three (Phase One) of the Windhoek-Okahandja road, which was supposed to have been completed in July 2016, will now be completed by the end of February 2017.
Portions of this road are expected to be open for traffic by mid-December this year.
Section Two of the same road which runs from Dobra River Bridge to Omakunde River Bridge just before the Osona Village, is progressing well with no suspensions issued.
Operations on the Windhoek-Hosea Kutako International Airport road extension have however been affected due to non-payment of some invoices, Fillemon noted.
The project extends from Sam Nujoma Drive through Kleine Kuppe and Auasblick to the traffic circle at the Rehoboth road, and continues on to the MR49 road leading to the Kupferberg landfill.
Other ongoing road projects are:
-Section A of the Gobabis-Aminuis-Aranos road. This project is currently 87 per cent complete and is envisaged to be completed by April 2017.
-Okamatapati – Grootfontein (Section 2): More than 50km of road has been surfaced and approximately 30km is open for use by the traffic.
-Swakopmund – Henties Bay: About 20 per cent of the 90km road has been completed. The project is expected to be completed in March 2018.
-Swakopmund – Walvis Bay: It is expected to be completed in January 2019.
-Henties Bay– Uis – Khorixas – Kamanjab: This section is currently under design and no contractors have been appointed.
-Karibib – Usakos: The road section is under design phase.
-Usakos – Arandis – Swakopmund: This section was advertised for detailed design and the RA is currently evaluating the submitted consultancy tenders.
-Okatana – Endola – Eenhana: The contractor on this project issued a notice to suspend works due to late payment. Fillemon said the issue is being addressed by the RA to ensure that all outstanding payments are settled and works continue as planned.
-MR92 – MR120 (Dual carriageway within Oshakati townlands): The project just recently commenced and is on schedule. The contract is expected to end in January 2018.
Other completed projects in this financial year include the Ruacana – Omakange road; Oshikuku – Onamutuku; Okalongo – Wakasamane; Omafo – Ongenga – Outapi; Liselo – Linyanti; Amwaanda-Omutambomawe; Oshigambo-Eenhana; Elundu-Eenhana.
(NAMPA)